NEW ANODIZING PLANT, AMS , LITTLE ISLAND, CO. CORK

Description


  • Installation of Free Issue Steam Boiler
  • Supply & Installation of all Sched 40 Steam Pipework
  • Supply & Installation of the Sched 10 stainless steel condensate lines
  • Supply & Installation of all Chilled Water Pipework from the main chiller unit
  • Supply & Installation of all Acid , Caustic , Permeate Water, Mains Water process line.
  • Supply & Installation of 180mts of 150m Natural Gas Pipework
  • Supply & Installation of flues , s/steel vents from steam equipment
  • Supply & Installation of Sanitary Ware
  • Office Ventilation & Air Con 
  • Supply & Installation of all Poly propane Extract System & Main Scrubber unit.

Client:

Architectural Metal Systems (AMS)


Consultant:

CDGA Engineering


Main Contractor:

MMD Construction